Hai Duong Power One Member Co., Ltd. on September 5 afternoon powered a 35 kV line from Nhi Chieu 110 kV substation to Hiep Son REC 01 in Kinh Mon provincial town.
The project to build a 35 kV line from Nhi Chieu 110 kV substation to Hiep Son REC 01 finishes two months earlier than planned
With a total investment of about VND11.5 billion, the project was commenced on May 15.
After more than three months of construction, the work was completed and put into operation safely two months earlier than planned.
The project consists of the installation of nearly 450 m of overhead double-circuit 35 kV line, close to 670 m of overhead four-circuit 35 kV line across the Kinh Thay river, 700 m of underground cable, etc.
The project will contribute to preventing the medium-voltage power grid in Kinh Mon provincial town and Kim Thanh district from being overloaded, improving the quality of electricity for loads in Hiep Son, An Luu, and Phu Thu in Kinh Mon, etc.
THANH HOA