Phase 2 of extended Dai An industrial park ready to welcome investment flows

DO QUYET 28/02/2024 09:20

Dai An Industrial Park (IP) Infrastructure Development Co., Ltd. is stepping up the construction of technical infrastructure to put phase 2 of the extended Dai An IP into operation.

img_8738.jpeg
The technical infrastructure of the extended Dai An industrial park (phase 2) has basically been built on 21.5 ha of land

Workers at the construction site of phase 2 of the extended Dai An IP project in Cam Giang district, Hai Duong province are busy working right in the first days of the new year.

Construction groups with dozens of workers and machinery are striving to accelerate the progress to soon put the project into operation.

Dai An IP Infrastructure Development Co., Ltd. is the investor of phase 2 of the project with a budget of about 2,300 billion.

The project covers a total area of 227 ha, including 187 ha in Cam Doai commune and 40 ha in Cam Dong commune, Cam Giang district.

img_8737.jpeg
Roads and lights are synchronously built

Deputy director of the company Luong Thanh Phong said 151 ha of land for phase 2 of the project have been cleared, accounting for 66.5% of the total area.

The construction unit has basically finished building technical infrastructure on 21.5 ha of industrial land, ready to lure investment in the near future, according to Phong.

Upon completion of phase 2 within this year, the extended Dai An IP will focus on attracting high technology, supporting, and light industries...

Many secondary investors with large investment and high technology are wishing to invest in phase 2 of the IP, according to the investor.